    Plan work tasks for the shift, track execution daily, document and report status for the next shift.

Overview

Implemented IA’s Project Controls product to track status of work tasks executed, field delays and lessons learned on a shift by shift basis.  Reports on LCD monitors at the workface facilitated shift hand-off of task status and field issues.

Top 3 pains:

  • Tracking daily activities
  • Documenting unplanned events
  • Clear communication between trailer and field

Results

Workface Efficiency® Delivered:

  • Focused planning of work on a shift-by-shift basis
  • Work execution tracking – time to execute tasks, status, lessons learned
  • Customized productivity, delay tracking and unplanned events reports
  • Communication to field through LCD monitor at the workface

 